The ASHRAE Level 1 and Level 2 reports
Choose the ASHRAE Level 1 or Level 2 report when a program asks for an ASHRAE Standard 211 energy audit. It adds the pages the standard asks for at that level, and a qualified energy auditor completes them after a site visit.
For: Analyzer (others: view-only)Where: Energy Auditing, Report in the building bar and the Site visit tab
- Which report to use
- Choose the report
- If the project doesn’t need to meet Standard 211
- The Site visit tab
- What the report adds
- Checks against the site visit and the bills
- Draft until it’s complete
- Download the PDFs
- What the auditor still decides
- Related
Which report to use
All three reports come from the same calibrated model and the same calculations.
- InverseAudit - The usual report. It needs no site visit, so it suits remote screening, owner reports and planning.
- ASHRAE Level 1 - What ASHRAE Standard 211 asks for a Level 1 audit: a site visit, a description of the building, the historical energy use with the benchmark and target, and the measure summary of low-cost and capital measures, with InverseAudit’s executive summary and utility analysis. It leaves out InverseAudit’s measure-by-measure results, which are Level 2’s. Use it when a program asks for a Level 1 audit only: the auditor has far fewer entries to make (about a third as many).
- ASHRAE Level 2 - Level 1 plus what the standard asks for a Level 2 audit: the building’s systems (envelope, HVAC, water heating, lighting and loads), an equipment inventory, the end use breakdown, and more about each measure and the package. Use it when a program asks for a Standard 211 Level 2 audit, for example C-PACE financing, LEED O+M or a city’s audit ordinance.
The standard doesn’t cover remote audits: every level needs a site visit by a qualified energy auditor. InverseAudit’s analysis alone isn’t a Standard 211 audit, which is why an ASHRAE report stays a draft until the auditor’s entries are done. When no program asks for the standard, see If the project doesn’t need to meet Standard 211.
Choose the report
- On Energy Auditing, choose the building.
- Next to Download PDF, click ASHRAE Level 1 or ASHRAE Level 2 under Report.
- Click Use ASHRAE Level 1 or Use ASHRAE Level 2 to confirm.
The page reloads with a Site visit tab, and the Download PDF menu lists the ASHRAE report’s parts. Each building keeps its own report type, and new buildings start on InverseAudit.
You can switch at any time. The site visit entries are shared by both levels, so moving from Level 1 to Level 2 keeps everything entered and adds Level 2’s entries; moving back keeps Level 2’s entries without printing them. Only the building’s analyzer can switch, and not while the audit is posted: unpost it first.
What Level 1 leaves out
At Level 1 the Site visit tab hides Envelope and Equipment inventory. HVAC asks only for the main HVAC system, its heating source, the controls and any HVAC observations; Water heating, lighting, loads only for the water heater found; and Measures and package only for measures without calculated savings. Items to verify are optional, and Facility and contacts doesn’t ask for the building shape or the walls by facing.
The Level 1 report’s Analysis is only the baseline model’s energy use by end use, and its Recommendations are only the measure summary: InverseAudit’s before-and-after end-use analysis, monthly costs and use, measure tables, utility rates, savings table and measure write-ups are left out, because a Level 1 audit doesn’t calculate each measure. The Analysis and Recommendations PDFs are the same. The measures are still entered and calculated on the Energy Auditing page, and the measure summary uses their figures.
The Level 1 report also leaves out Level 2’s pages: Building envelope, HVAC systems, Water heating, lighting and other loads, Equipment inventory, the walls by facing, the End-use breakdown, Renewable and distributed energy, and Level 2’s Recommendations pages (the review with the owner, the cost breakdown, the Level 2 measure summary, the savings by measure and the QA/QC check, the package, M&V and Level 3). Its cover and compliance form say Level 1.
If the project doesn’t need to meet Standard 211
Some clients want the ASHRAE report’s pages without a Standard 211 audit, for example when the audit is remote. On the Site visit tab, open Compliance page and untick This project must meet ASHRAE Standard 211. The box is ticked unless you untick it.
With the box unticked:
- Every site visit entry is optional. The entries you make are printed and empty ones aren’t, so the report is never a draft. Each section shows how many entries are made instead of how many are left.
- Missing bills don’t make the report a draft. The historical energy use pages still say which bills are missing.
- The report doesn’t name Standard 211. The cover says “Level 2 energy audit” (or Level 1), and so does the audit overview. The auditor’s statement certifies that the report is complete and correct, and mentions a site visit only if its date is entered. The tables keep the standard’s layout, but their notes don’t refer to its forms.
- The compliance form (Form A) is left out, and so are the entries only it uses: the qualification route, the audits completed and, at Level 2, the Level 1 date. In Download PDF, Cover and compliance becomes Cover page.
You can tick the box again at any time, and nothing you entered is lost. Like the other entries, it locks while the audit is posted.
The Site visit tab
The qualified energy auditor fills in the Site visit tab after visiting the building. Its sections are listed on the left, each with how many of its entries are done:
- Site visit and interviews - The dates, who was there, the areas and systems visited, what was checked, the interviews, operation and maintenance observations, and the main findings for the Executive summary.
- Items to verify - What the owner or operator provided and what the calibration found, for the operating hours, setpoints, lighting, heating, cooling, outside air and water heating. Type what they gave you (drawings, BAS printouts, interviews) in Provided. With monthly bills it starts from the Systems dialog, and reset to the Systems dialog puts that value back. Provided is for the report only: it doesn’t change the model. Tick Confirmed when the site visit agrees with the model, or write what was found. A ticked item’s figures print as Modeled, verified instead of Modeled, verify. Recalibrating clears the ticks, since the calibrated values can change; what you wrote is kept.
- Facility and contacts - Renovations, earlier audits, landmark status, the owner and bill payer, other space types, the occupancy schedule, and the walls on each side of the building.
- Envelope, HVAC and Water heating, lighting, loads - What the model can’t know, such as construction, condition, controls and nameplates.
- Equipment inventory - The units installed, one row for each unit or group of identical units.
- Utility accounts and rates - Account and meter numbers, and the tariffs; and, when a utility isn’t calibrated, the Calibration follow-up (see When a utility isn’t calibrated).
- Measures and package - The review with the owner, planned dates, reasons for measures not evaluated, funding, O&M and M&V costs, and the assessment of solar PV and combined heat and power.
- Compliance page - Whether the project must meet ASHRAE Standard 211, the building owner, the auditor and their qualification, and the dates the Level 1 and Level 2 audits were completed. A date left empty prints as the Assessment Date, the day the audit is posted.
Each entry saves when you leave it. For tables, click Add a row to add a row and × to remove one. The entries lock while the audit is posted, and only the building’s analyzer can change them. The number on the tab is how many entries are still empty.
An entry left empty isn’t printed, and neither is its title. A table or column with nothing else in it is left out too. The exception is the compliance form (Form A): it keeps all its lines, blank where nothing is entered, so it can be filled in by hand.
Narratives
Envelope, HVAC and Water heating, lighting, loads each have narratives for describing the building as found, for example “Systems installed” for the HVAC. They’re optional, so a narrative left empty doesn’t keep the report a draft.
Measure text and priorities
The reports use InverseAudit’s text for each kind of measure: its comfort, other non-energy and O&M impacts and, at Level 1, the system it changes. Under Measures and package, the auditor can replace that text for this building, and at Level 1 a measure’s priority.
The measure summary with Low, Medium and High bands and a priority is Level 1’s form (L1 - EEM Summary). The Level 2 report has the standard’s Level 2 form instead (L2 - EEM Summary), with each measure’s savings, cost, life, ROI and payback. It opens the Recommendations section, as the same table does in the InverseAudit report, where only the non-energy cost savings column is left out. The comfort and other non-energy impacts are in the Level 2 report’s Other impacts and planned dates table.
What the report adds
| Where | What |
|---|---|
| Cover | The Standard 211 Level 2 title, the site visit date and the auditor’s statement |
| After the cover | The compliance form (Form A) |
| Executive summary | An audit overview at the top: scope, energy data, method, key dates, contacts, energy use and the recommended package |
| New sections after the Executive summary | Site visit and interviews, Facility description, Building envelope, HVAC systems, Water heating, lighting and other loads and Equipment inventory |
| Analysis | Opens with energy use by end use with all fuels, before and after the measures, and the End-use breakdown of each fuel with each end use’s peak kW, in place of InverseAudit’s electricity end-use charts and tables. Ends with Renewable and distributed energy. The utility rates are in Historical energy use |
| Recommendations | The Level 2 measure summary (the standard’s L2 - EEM Summary) at the top, in place of InverseAudit’s recommendations table, then the measure write-ups, the review with the owner, the cost breakdown (material, labor and markup), the other impacts and planned dates, measures considered but not recommended, the savings by measure and end use with the QA/QC check, the recommended package, where the savings come from, measurement and verification, and measures for a Level 3 analysis |
| Utility analysis | Historical energy use (accounts, rates, the measured data and the benchmark) and Calibration results. A bill whose cost isn’t on the meter data is estimated in grey at the average rate: the year’s cost ÷ use at the building’s rates. InverseAudit’s EUI and costs by year come first only when the building has more than one year of data |
Each figure is marked with where it comes from: Model (the building’s inputs and model), Modeled, verify (estimated by the calibration, for the auditor to check), Modeled, verified (ticked Confirmed under Items to verify), Calculated, or Auditor.
Equipment as the model’s totals
The calibrated model simplifies the building’s geometry and systems; for example, it may have one air handler per floor. So the report gives equipment as the model’s totals, such as the total cooling capacity, supply air and fan power. The auditor lists the units actually installed in the equipment inventory, and the report adds up their nameplate capacities next to the model’s totals.
When a utility isn’t calibrated
Sometimes the calibrated model can’t match a utility’s meter data, even though it reflects the building as documented. The report then says so, for the owner to check:
- Natural gas or another fuel - when the year’s total of the bills and the model’s, over the same billing periods and with the same weather, differ by more than 5%.
- Electricity - when the NMBE is outside the ASHRAE Guideline 14 limit: ±5% for monthly bills, ±10% for hourly data.
The audit overview’s Method names the utility, and the executive summary says what its bills show against the model, with finding out why as the first next step. Under Calibration results, a section for the utility lists its bills against the model, points out where most of the difference falls and any bill with an unusual period (under 20 or over 40 days), and gives the possible causes and what to check. The utility’s use, end uses and savings in the report are from the model. When the bills are higher than the model, the section also gives what the excess costs a year at the building’s average rate.
The Site visit tab then has an optional Calibration follow-up entry under Utility accounts and rates, for what was checked and the owner’s answer. It prints in that section.
Checks against the site visit and the bills
The report compares the model with what the site visit found and with the bills, and points out where they disagree, in dark orange. None of these checks changes the model: they tell the auditor what to look at.
Site visit questions. Under HVAC and Water heating, lighting, loads, these choices record what the site visit finds:
- Main HVAC system - The system that serves most of the floor area: Packaged rooftop units, Split systems, Furnaces with air conditioning, Central plant with air handlers, Fan coils, Heat pumps, Packaged terminal units (PTAC, PTHP), Mini-splits or VRF, Window or wall units, Heating only, or Other. Both levels, optional.
- Heating source - Natural gas, Electric resistance, Heat pump, Oil or propane, District steam or hot water, or None. Both levels, optional.
- Water heater found on site - None, Electric, Gas or other fuel, Heat pump, or Not known. Both levels, optional.
- Outside air dampers when unoccupied - Close, Stay open or Not known. Level 2 only, optional.
- Economizer as found - Its changeover and whether it runs with the compressor. Level 2 only, optional.
At Level 1, HVAC also asks for the Controls (a building automation system, programmable or manual thermostats, time clocks, or none; Level 2’s Building automation) and, optionally, HVAC observations: what stood out, such as units running after hours, dampers stuck open, overridden thermostats or comfort complaints. In the PDF, the Facility description’s HVAC table, after Space functions, gives the model’s system next to the main HVAC system and heating source found, and at Level 1 the controls and the observations.
Differs notes. Under Items to verify, a model value that disagrees with the site visit gets a Differs: note, on the tab and in the PDF:
- the main HVAC system, the heating source, the dampers, the economizer or the water heater, against the answers above;
- an equipment inventory whose cooling or boiler capacity is more than 20% from the model’s;
- a gas furnace efficiency or a DX cooling EER below the federal minimum for the year the units were installed. The year comes from the equipment inventory, or else from the HVAC condition or a renovation that names the HVAC. Units under 65 kBtu/h have no federal EER and aren’t checked.
At Level 2, when the dampers are found to close already, the outdoor-air damper measure says so: Site visit: the dampers already close when unoccupied, so it may save nothing. Confirm or remove it.
Rates against the bills. In the utility rates table, each rate gets a line on how the bills compare with it, from at least 6 bills: when it fits, a fixed amount a bill plus a cost per unit, and how many bills come out more than 10% off their cost at the rate entered. For electricity with a flat rate, it also notes demand recorded on the bills with no demand charge, and the tariffs in InverseAudit’s rate database for the state. The measures are valued at the rate entered: to value them at what the bills show, enter the per-unit rate or the tariff in Rates and run the measures again.
Gas above the model. When the gas bills are higher than the model (see When a utility isn’t calibrated), the causes start with A gas leak, a safety item to check first. Each bill’s use a day is then compared with heating degree-days (base 65 °F): Heating runs more than documented when the bills follow the weather, A load that runs whatever the weather when they don’t, or both. A gas water heater found on site that the model doesn’t have is listed too.
Humid climates. In climate zones 0A to 3A, a setpoint measure with a cooling setback above 80 °F adds a caution to its comfort impact: humidity can build up over long closed periods. Text you changed yourself stays as you wrote it.
Report checks. The page header lists what to fix before the report goes out, for example ENERGY STAR score out of date, a completion date before the analysis, or a flat rate entered that’s far from the bills. A stale ENERGY STAR score is recalculated when you open Energy Auditing.
Measured first. The executive summary starts with what the bills show, then the model as the building as documented. The ENERGY STAR score and the costs are labelled as the model’s.
Draft until it’s complete
While any required site visit entry is empty, or the energy data is incomplete (for example, natural gas is used but there are no gas bills), the report is a draft:
- Empty entries don’t print, so the Site visit tab is where to see which are open.
- Every page header says DRAFT, with how many site visit items are open and what data is missing.
- The compliance form shows Not yet for the standard’s requirements, and its signature lines are marked not to be signed.
- Full report in the Download PDF menu shows how many items are open.
Enter 12 months of bills for each fuel on the building’s meter data to complete the energy data. See Meter data.
Download the PDFs
Under Download PDF, both ASHRAE reports have Full report, Cover and compliance, Executive summary, Site visit and facility, Analysis, Recommendations, Utility analysis and, for US buildings, Appendix A: ESG/carbon. The parts show the same pages as in the full report. The full report leaves out Appendix B (the carbon impact of each measure), which the standard doesn’t ask for; it stays in InverseAudit’s report and on the Recommendations tab. See Reports and PDFs.
What the auditor still decides
- Measures without calculated savings - Keep each, with the reason, or drop it.
- Measures not evaluated - Where the building is below the energy code and no measure was run, give the reason. A measure is listed as not recommended, with no reason needed, when the building already meets the code.
- Priorities - They come from the payback. The cost, savings and ROI bands are InverseAudit’s, not values from the standard.
- Solar PV and combined heat and power - The report sizes them and asks for the auditor’s assessment. Solar PV savings come from the Solar PV measure, when you run it; combined heat and power needs a Level 3 study.
- Costs - Material, labor and markup come from the cost table’s shares for each kind of measure. A cost typed in on the Recommendations tab is shown as its total.
Check the standard’s own reporting forms and the program’s requirements before you submit the report.